What the PLC Must Coordinate on a 5-Gallon Water Line
A jar-line controller coordinates indexing, washing, filling and cap application. The sequence must match the physical position of each container and the required process conditions. A PLC brand does not demonstrate that all stages occur correctly.

Check position and process together
Compare station presence signals with actual jar locations. Confirm that a missed index, absent jar or interrupted utility produces the intended response. Test these conditions through the approved commissioning procedure, without bypassing protective functions.
Record the completed route
Keep washing conditions and relevant alarms linked to the production period. Inspect jars and closures at discharge. A rising production counter is not sufficient evidence that every container passed through the required washing and filling sequence.
Need help planning your packaging line?
Share your product, bottle and capacity requirements for a practical equipment recommendation.