Preparing the Site for a Beverage Tunnel Pasteurizer
A tunnel pasteurizer needs the approved product-package process, conveyor arrangement, utilities and drainage. A container-height limit alone is insufficient to determine whether a package is suitable for the intended thermal cycle.

Plan the installed route
Check entry and discharge heights, service access, spray-water management and the route for rejected or held product. Include utility conditions at simultaneous production demand, not only an unloaded supply reading.
Commission against the process
Measure the required product-temperature history using the approved method. Inspect spray coverage and package condition across the conveyor. Mechanical installation and validated treatment acceptance are separate completion items.